Modular Classroom Complex

[CHALLENGE]
In order to efficiently complete the phased renovation required for an elementary school and the construction of a new middle school, a large modular classroom building was required. The site was tight with little lay down area for the construction and assemble of the modular school.

[SOLUTION]
Modular Genius constructed a 13,056 square foot modular classroom complex for the project. The size of the modular building required a fire wall be installed for life safety. The turn key services provided by Modular Genius for the project included engineering, permitting, foundations, mechanical, plumbing, electric and communication connections. The project was complete in 150 days from award to occupancy.

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s