Medical Modular Building

[CHALLENGE]
The US Marine Corp Bureau of Medicine and Surgery (BUMED) was in need of additional administrative and storage space for vaccines. The vaccines had to be kept at a particular temperature to maintain stability of the medicine.

[SOLUTION]
Working with an 8a contractor Modular Genius provided a 3,600 sq ft modular building along with prefabricated ramps and ADA prefabricated aluminum steps. The project was completed in 60 days from notice to proceed.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s